Please start any new threads on our new
site at https://forums.sqlteam.com. We've got lots of great SQL Server
experts to answer whatever question you can come up with.
Author |
Topic |
HaoVV
Starting Member
1 Post |
Posted - 2011-09-27 : 06:17:52
|
hi all, I got a big problem about log shipping, I don't know how to get exactly next run time of copy and restore job.example: first of all (Copy job): I configure copy job last run: 10:12:00 next run: 10:22:00(frequency 10 minute)then, I want to reconfigure with frequency 15 minute. but I got result below:last run: 10:12:00next run: 10:18:00(exactly result must is : last run: 10:12:00 next run: 10:27:00)I don't know why?please help me to clear it. thanks so much!(My English too bad )--Vo Van Hao |
|
biswajitdas
Starting Member
44 Posts |
Posted - 2012-01-11 : 14:00:21
|
did you reconfigure the job at 10:03:00 ?Sr Sql server DBA/Artitech |
|
|
tkizer
Almighty SQL Goddess
38200 Posts |
|
|
|
|