gaktheknife
Starting Member
12 Posts |
Posted - 2015-04-29 : 10:14:37
|
I use the following expression to account for weekends when outputting to excel. How can i get this to be just the date like 20150429 instead of the full start time.((DT_I4)DATEPART("weekday",@[System::StartTime]) ==2 ? Replace((DT_STR, 20, 1252)(DATEADD( "D", -3,@[System::StartTime])),":","") + ".xlsx" : Replace((DT_STR, 20, 1252)(DATEADD( "D", -1,@[System::StartTime])),":","") + ".xlsx") |
|
gbritton
Master Smack Fu Yak Hacker
2780 Posts |
Posted - 2015-04-29 : 11:11:13
|
[code]LEFT( REPLACE( (DT_STR, 20, 1252)(DATEADD( "D", (DT_I1)DATEPART("weekday",@[System::StartTime]) ==2 ? -3 : -1, @[System::StartTime])),"-","") ,8) + ".xlsx"[/code] |
|
|
gaktheknife
Starting Member
12 Posts |
Posted - 2015-04-29 : 11:43:33
|
Awesome! Thank you |
|
|
|
|
|
|
|